Santiago Bernabéu
Real Madrid’s ground, fully modernised (retractable roof, retractable pitch), is the Spanish front-runner to host the 2030 final.
Spain · Valencia
Work resumed in 2025 after sixteen years on hold: 70,044 seats, with handover targeted for July 2027. Put to FIFA in March 2026 as a replacement for Málaga.
Started in 2007 then abandoned for some fifteen years, the Nou Mestalla restarted in January 2025 with the contractor FCC. The 70,044-seat stadium will be the one of the largest in Spain. The compression ring, 50 steel columns weighing 30 tonnes each and the roof structure (4,800 tonnes) were finished in June 2026; the site was announced as 75% complete in July 2026.
On 26 March 2026, the Spanish federation put Valencia and Vigo to FIFA as replacements for Málaga and A Coruña. On 2 April, Valencia city council approved the agreement allowing the stadium to be used. FIFA is due to inspect the site in the autumn of 2026, once it has opened its permanent office in Spain; “the decision rests exclusively with FIFA” (El Desmarque, 20 July 2026).
Target handover: summer 2027 (11 July 2027 according to El Desmarque), in time for the 2027-2028 season.
The stadium stands on Avinguda de les Corts Valencianes, north-west of the centre, near the Benimàmet / Beniferri metro station (lines 1 and 2). Final transport arrangements to be confirmed when it opens.
Last checked : 30 August 2026
Real Madrid’s ground, fully modernised (retractable roof, retractable pitch), is the Spanish front-runner to host the 2030 final.
Atlético’s 70,692-seat stadium has already hosted a Champions League final (2019). Its participation in 2030 has been described as “in doubt” by the Spanish press.
Mid-rebuild, the Camp Nou is reopening in stages: 62,652 seats licensed since March 2026, with a target of 104,600 covered seats by late 2027 – early 2028.